7 Steps to Conduct a CDM 2026 Site Audit
Last Updated: 4 November 2026
Quick Summary
To conduct a CDM site audit, define your scope and objectives, build a checklist from the Construction (Design and Management) Regulations 2015, then walk the site testing documents against reality. Record evidence for every finding, prioritise by risk, and assign each action a named owner and due date before validating the fix.
- Agree what pass means for each checklist item before anyone walks the site.
- Derive checklist questions duty by duty from the Construction (Design and Management) Regulations 2015.
- Interview at least three people, including a supervisor, a trade operative and the first aider.
- Score findings on likelihood and consequence, treating high-rated items as stop-work territory.
- Validate remediation by checking the fix itself, not an email confirming it.
Table of Contents
- Step 1: Define the Scope and Objectives of Your CDM Site Audit
- Step 2: Build Your CDM Site Audit Checklist
- Step 3: Run a Construction Site Safety Audit on the Ground
- Step 4: Carry Out a Construction Phase Plan Audit
- Step 5: Check CDM Health and Safety File Requirements
- Step 6: Record Evidence and Prioritise Findings by Risk
- Step 7: Assign Remediation, Validate Actions and Monitor
- Book CDM 2015 Training to Sharpen Your Audit Skills
- Frequently Asked Questions
Step 1: Define the Scope and Objectives of Your CDM Site Audit
A CDM site audit is a structured check of how well a construction project meets its duties under the Construction (Design and Management) Regulations 2015.
So start there. Write down what the audit must prove.
- Which project phase you are auditing: pre-construction, construction, or handover
- Which duty holders fall in scope: client, principal designer, principal contractor, contractors
- Which evidence you expect to see: plans, records, inspections, training certificates
- What “pass” means for each item, agreed before anyone walks the site
Keep the scope tight. An audit that tries to cover every project on a framework produces a report nobody reads.
The Construction (Design and Management) Regulations 2015 set out the legal duties you are testing against, so anchor your objectives to them rather than to a generic checklist.
Watch out: auditing against your own memory of the regulations rather than the current text is the most common way to miss a duty entirely.
Step 2: Build Your CDM Site Audit Checklist
A CDM site audit checklist is not a generic site inspection sheet. Mapping each duty to evidence also makes it easier to distinguish a CDM audit from a broader construction site inspection, where preparation should reflect the checks being carried out.
The most common mistake is to copy a checklist from another project or a generic template. That produces findings that cannot be tied to a specific regulation, which makes remediation harder to justify and defend.
How to derive checklist items from the regulations
Work through the regulations duty by duty. For each duty, write one or more questions that can be answered with evidence. For example:
- Regulation 8 (client duties): Has the client appointed a principal designer and principal contractor in writing? Is the F10 notification submitted where required? Can the client produce the pre-construction information they provided?
- Regulation 11 (principal designer): Is there a design risk register? Are design team meetings minuted with risk decisions recorded? Can the principal designer demonstrate coordination of design work?
- Regulation 12 (principal contractor): Is the construction phase plan signed before work started? Are site induction records available? Are inspection records kept for the site?
- Regulation 15 (contractors): Can the contractor produce RAMS for high-risk activities? Are operatives’ training and competence records available? Are briefings recorded?
Each question should have a clear pass condition agreed before the audit. “RAMS available for all high-risk activities” is testable; “good safety culture” is not.
Structuring the checklist
Group items by dutyholder and by project phase. A practical structure is:
| Checklist area | What you are testing | Evidence to collect |
|---|---|---|
| Client duties | Appointments, notification, pre-construction information | Appointment letters, F10 record, information pack |
| Principal designer | Design risk management, coordination | Design risk register, meeting minutes, design review records |
| Principal contractor | Construction phase plan, site management, induction | Signed plan, induction records, inspection records |
| Contractors | Competence, supervision, RAMS, briefings | Training certificates, RAMS, briefing sheets |
| Site conditions | Housekeeping, access, welfare, plant, work at height | Photos, walkthrough notes, maintenance records |
| Health and safety file | Content, currency, ownership | File index, document register, owner confirmation |
Add three columns to every row: a score (compliant, partial, not met), an owner (named person), and a due date. A finding without an owner and a date is a note, not an action.
Scoring and evidence rules
Score each item against the pass condition you agreed in Step 1. For a partial score, record exactly what is missing. For a not met score, record the regulation and the evidence gap. Attach a photo, document reference, or interview note to every finding.
Watch out: building the checklist from memory rather than from the current text of the regulations is the most common way to miss a duty entirely, especially where duties have been clarified by case law or guidance since the regulations were made.
Step 3: Run a Construction Site Safety Audit on the Ground
A construction site safety audit on the ground is where paperwork meets reality. Walk the site with the checklist in hand and test what the documents claim.

What to Observe on the Walkthrough
Look at the physical conditions first, before anyone has a chance to tidy up.
- Access and egress: clear routes, signed, lit
- Housekeeping: waste, trailing cables, blocked walkways
- Welfare: toilets, washing, drinking water, rest area
- Plant and equipment: guards in place, operators ticketed
- Work at height: edge protection, ladders, scaffolds tagged
- Hazardous substances: storage, labelling, asbestos awareness
Photograph what you find. Our guide to identifying and solving site hazards goes deeper on the hazards this walkthrough only touches. Keep our list of common health and safety violations to hand so you know what to look for and how to avoid them. A photo with a timestamp is evidence; a description is an opinion.
Who to Interview and What to Ask
Talk to at least three people: a supervisor, a trade operative, and whoever holds the first aid duty.
Ask open questions. “Show me how you’d report a near miss” tells you more than “do you know the procedure”.
Watch out: interviewing only the site manager gives you the version of the site that exists in the site office, not the one people work in.
Step 4: Carry Out a Construction Phase Plan Audit
A construction phase plan audit checks whether the plan is live, signed, and actually followed. Most plans we see are well written and out of date.
Test four things:
- Is it signed by the principal contractor before work started?
- Does it match the site as it stands today, not as it was scoped?
- Are arrangements named for supervision, welfare, first aid and emergencies?
- Can the site team describe it without reading it?
If the answer to question four is no, the plan is a document, not a management tool. Mark it partial and say why.
Step 5: Check CDM Health and Safety File Requirements
CDM health and safety file requirements are the records the client must keep for the life of the building, covering design, construction and future maintenance. Check it exists, check it is current, and check someone owns it.
- As-built drawings and structural information
- Materials used, including hazardous ones
- Maintenance and cleaning instructions
- Residual risks that future workers need to know
Where a project falls under the higher-risk regime, the file also feeds into the golden thread of information.
Step 6: Record Evidence and Prioritise Findings by Risk
Evidence turns an audit into something you can defend. For every finding, record the duty, the condition, the evidence (photo, document reference, interview note), the person you spoke to, and the date. Then prioritise by risk, not by how easy the fix is.
Most audits lose their value here. A report with forty findings and no ranking gets filed and forgotten. A report with ten findings, each scored, owned, and dated, gets closed out.
Building the evidence log
Use a simple evidence log with one row per finding. At minimum, capture:
- Finding reference: a unique number you can cite in the report and in follow-up emails
- Dutyholder and regulation: who owns the duty and which regulation applies
- Condition observed: what you saw, in plain language
- Evidence type and reference: photo number, document title, interview note
- Date and location: when and where you observed it
- Initial risk rating: see the scoring method below
- Owner and due date: named person and target date for the fix
- Status: open, in progress, closed, verified closed
A spreadsheet is sufficient. The discipline matters more than the tool.
Scoring likelihood and consequence
Score each finding on two axes: likelihood (how probable is harm or non-compliance if nothing changes) and consequence (how severe would it be). Use a simple three-point scale for each:
- Likelihood: low (unlikely in the next phase), medium (possible), high (likely or already happening)
- Consequence: low (minor record gap), medium (duty not met but no immediate harm), high (serious harm or stop-work territory)
Combine the two scores into a risk rating:
| Likelihood | Consequence | Rating |
|---|---|---|
| High | High | High |
| High | Medium | High |
| Medium | High | High |
| Medium | Medium | Medium |
| Low | High | Medium |
| High | Low | Medium |
| Medium | Low | Low |
| Low | Medium | Low |
| Low | Low | Low |
High-rated findings are stop-work territory: act today, and record the action. Medium-rated findings should be fixed within the current project phase. Low-rated findings can be fixed at the next review.
From risk register to verified closure
A risk register is only useful if actions close. For each finding, assign one named owner and one due date. Then validate: go back and check the fix, not just the email that says it is done.
Monitor by repeating the check at a set interval with the same checklist, so you can show improvement over time and catch regressions.
Step 7: Assign Remediation, Validate Actions and Monitor
Remediation only works when one named person owns each action and a date sits against it. Assign, then validate, then monitor.
Validation means going back and checking the fix, not accepting an email that says it is done. Monitoring means a repeat check at a set interval, with the same checklist, so you can show improvement over time.
Supervisors carrying these actions need the authority and knowledge to lead them. Our SSSTS guide shows how the course helps supervisors lead safety fixes with confidence.
Book CDM 2015 Training to Sharpen Your Audit Skills
An audit is only as sharp as the person holding the clipboard.
If your team needs to test CDM duties with confidence, You Can Do It Training offers training in CDM 2015, SMSTS and SSSTS, with courses designed to avoid disrupting construction programmes. You can book a course to find out more.
Get started with You Can Do It Training and turn your next site audit into a set of actions people actually close.
Frequently Asked Questions
What should a CDM site audit include?
A CDM site audit should cover the construction phase plan, site safety arrangements, welfare provision, statutory inspections, the health and safety file and evidence of consultation with workers. It should also check that the principal designer and principal contractor have recorded their duties in writing. The audit needs a defined scope, a checklist, documentary evidence and a clear record of findings so that actions can be assigned and followed up.
What is the difference between a CDM audit and a site inspection?
A site inspection is a snapshot of conditions on a given day, such as housekeeping, edge protection or PPE use. A CDM site audit is broader: it tests whether the management arrangements required under CDM 2015 are in place and working, including the construction phase plan, the health and safety file, worker consultation and the competence of duty holders. Inspections feed the audit, but they do not replace it.
Does CDM 2015 still apply in 2026?
Yes. The Construction (Design and Management) Regulations 2015 remain the governing regulations for construction projects, and the duties on clients, principal designers, principal contractors, designers and contractors continue to apply. When planning a CDM site audit in 2026, use the 2015 Regulations as your reference point and check that your audit checklist reflects the current version of the regulations and any updated industry guidance.
How often should a construction site be audited?
There is no single frequency that fits every project. Set the interval from risk: a high-risk project with multiple contractors may need a monthly audit, while a smaller refurbishment might suit a quarterly cycle plus a review at each key stage. Increase frequency after an incident, a near miss or a significant change in the construction phase plan, and always audit before handover so the health and safety file is complete.