7 Steps to Notify HSE of a Construction Project

Last Updated: 7 November 2026

Quick Summary

To notify HSE of a construction project, submit an F10 notification through the HSE online service before the construction phase begins. The client holds the legal duty to notify, though the principal designer or principal contractor often submits it on their behalf. A project is notifiable if it lasts more than 30 working days with over 20 workers on site at once, or exceeds 500 person-days.

  • The client holds the legal duty to notify HSE, even when someone else submits the F10.
  • Submit the F10 before the construction phase starts, not on day one or after mobilisation.
  • The 30-day test needs both more than 30 working days and more than 20 workers on site together.
  • The maximum workforce figure is a peak, not an average or total project headcount.
  • Update the notice through the same HSE service whenever project details change.
Not sure if your project needs an F10?We train site teams on CDM 2015 notification duties and compliance, without disrupting your programme.

Book CDM Training

Table of Contents

What a Notification to HSE Actually Is

A notification to HSE is a formal written notice that a construction project meets the legal threshold for notifiable work under the Construction (Design and Management) Regulations 2015.

The notification is not an application. HSE does not approve it, and no permission comes back. It is a declaration, and the duty sits with the client.

Under the CDM Regulations 2015 guidance from HSE, notification is required before the construction phase begins, and the information must stay accurate for the life of the project.

The F10 Notification Threshold: Deciding If Your Project Qualifies

A project is notifiable if construction work lasts more than 30 working days and has more than 20 workers on site at the same time, or exceeds 500 person-days of construction work at any one time (What you need to know if you are doing or having construction and building work carried…).

The threshold is the part most teams get wrong. Two tests apply, and you only need to pass one.

The 30-Day and 20-Worker Test

This test needs both conditions met together:

  • Construction work runs for more than 30 working days
  • More than 20 workers are on site at the same time on any day

Short projects do not qualify under this limb, even with a big workforce. Long projects with a small crew do not qualify either.

The 500 Person-Day Test

The second limb catches projects that are large in total effort but spread thin.

Person-days means one worker for one day. Ten workers for fifty days is 500 person-days. The test looks at the whole construction phase, not a single day.

For a broader look at how CDM 2015 duties fit together, our construction health and safety guide walks through the full framework.

Scenario Duration Peak workers Person-days Notifiable?
Small extension 20 days 8 160 No
Long fit-out 45 days 12 540 Yes, 500 person-days
Busy site 40 days 25 1,000 Yes, both limbs
Short refurb 25 days 30 750 Yes, 500 person-days

Person-days

Small extension 160
Long fit-out 540
Busy site 1,000
Short refurb 750

Who Submits an F10 Notification

The client holds the legal duty to notify HSE. In practice, the client often asks the principal designer or principal contractor to submit the F10 on their behalf.

When roles are unclear or change mid-project, notices fall through the cracks.

Our advice: put notification in writing as a named task, with a named person and a date. That single line prevents most gaps.

When to Submit Before Work Begins

Submit the F10 notification before the construction phase starts. Not on day one, not after mobilisation. Before.

The notice needs to be in place early enough that HSE has the project details on record from the outset.

Leaving notification until the pre-start meeting is too late.

If a breach does occur, our guide to how courts set HSE fines for safety breaches explains how penalties are calculated.

How to Complete an F10 Form Online, Field by Field

The F10 form is completed online through the HSE notification service. Work through it in order, have your project information to hand, and save nothing for later.

Construction site manager filling in an F10 form online to notify HSE on a laptop in a site office.
Construction site manager filling in an F10 form online to notify HSE on a laptop in a site office.

Here is how the fields break down and where teams most often go wrong:

  1. Notifier details – name, role, and contact details for the person submitting. This is the person HSE will contact if there is a query, so use a role-based inbox or a named individual who will still be in post when the project starts. Watch out: a personal email that goes dormant after mobilisation is a common cause of missed HSE correspondence.
  2. Client details – the client’s name and address. For a company, use the registered name and address, not a trading name or a site address. If the client is a domestic householder, the client is still the client for CDM purposes, and their details go here.
  3. Principal designer and principal contractor – names and addresses where appointed. If appointments are not yet made when you notify, state that clearly rather than leaving the field blank or guessing. The notification can be updated later, but an incorrect named party is harder to unpick than an honest “not yet appointed”.
  4. Project details – site address, a short project description, and the planned start date. The site address should be the address a worker would put into a satnav, including the postcode. The description should be plain enough for an inspector to understand the scope without site knowledge – “two-storey rear extension and internal refurbishment” is better than “works as per drawings”.
  5. Project duration – expected length of the construction phase in working days. Count working days, not calendar days, and exclude weekends and public holidays. If the programme is not fixed, use the best current estimate and plan to update it.
  6. Maximum workforce – the largest number of workers expected on site at any one time. This is a peak figure, not an average and not a total headcount across the project. Count everyone who will be on site carrying out construction work on the busiest day, including subcontractors.
  7. Person-days – the total construction effort across the project. Multiply the expected number of workers by the number of days they will each work, then add the figures for each trade or phase. This is the figure that most often decides whether a borderline project is notifiable at all.

The live form times out after a period of inactivity, and unsaved changes are lost.

For the wider set of duties around reporting, our RIDDOR reporting guide covers the separate incident reporting rules.

Information You Need to Hand

Gather these before you open the form:

  • Site address and postcode
  • Client name and contact details
  • Principal designer and principal contractor details, or confirmation that appointments are pending

A common mistake is starting the form without the workforce and person-day figures. Those two numbers decide whether the project is notifiable at all, so work them out first. A second is treating the maximum workforce figure as a total headcount, an inspector will expect it to reflect the busiest day on site, not the total number employed across the project.

A Pre-Flight Check Before You Submit

Before you press submit, run through these five checks. They catch the errors that most often lead to a query or a correction:

  • The site postcode matches the address you have written, not the client’s head office postcode
  • The start date is the construction phase start date, not the contract award or mobilisation date
  • The maximum workforce figure is a peak, not an average

If any of these cannot be answered confidently, the notification is not ready. Submitting a notice you know is wrong creates more work than waiting a day to get the figures right.

Updating an F10 Notification After Details Change

The notification must stay accurate for the life of the project. If the project details change, update the notice. The duty to keep the notice current sits with the client, in the same way as the duty to submit it in the first place.

You update through the same HSE service used to submit the original notice, retrieving the existing notification and amending the details rather than starting a new one.

What Counts as a Change Worth Amending

Not every change on site requires an amendment, but the following do, because they affect the information HSE holds about the project:

  • A new principal contractor or principal designer appointed after notification
  • A revised construction phase start date
  • A change to the maximum number of workers on site at any one time

Changes that do not affect these fields – a new site manager, a revised RAMS, a change of subcontractor within the same trade – generally do not require an amendment, provided the maximum workforce and person-day figures remain accurate.

Watch out: a change of principal contractor is the amendment most often missed. The outgoing contractor assumes the incoming one will update the notice, and the incoming one assumes it has already been done.

Correcting an Error After Submission

If you spot a mistake after submitting, a wrong postcode, a start date entered as a calendar date rather than a working day, a person-day figure that was estimated rather than calculated, correct it through the same service rather than leaving it. An accurate amended notice is better than an original notice you know is wrong. Keep a note of what was corrected and why, so the site file tells a coherent story if reviewed.

Cancelling a Notification

If a project is cancelled or does not proceed, the notice should be dealt with rather than left standing. A stale notice on record suggests the client is not actively managing the project’s CDM duties. Use the same service to cancel or withdraw the notification, and record the cancellation in the site file alongside the original submission confirmation.

Keeping Records of Changes

For each amendment, keep:

  • The date of the change
  • What changed and why
  • Confirmation that the amendment was submitted

Store these with the original submission confirmation and the displayed notice. If HSE or an inspector asks for the project’s notification history, a single file showing the original notice, each amendment and any cancellation is far easier to defend than a scattered email trail.

Displaying the Notice and Keeping Records on Site

A copy of the notification must be displayed on site where workers can see it. The notice is a legal record, and inspectors expect to find it.

Keep these with the site file:

  • A copy of the submitted F10
  • Confirmation of submission
  • Records of any updates

Store the file where the site manager can reach it quickly. Digital copies are fine, but the displayed notice should be visible on site.

Get Your Team Ready to Notify HSE with Confidence

Notification is one duty among many, and it only works when the people running the site understand the full picture.

Our courses are built around that practical knowledge. Expert instructors cover CDM 2015 duties, and our courses are designed to avoid disrupting your construction programme.

If your supervisors need to understand notification and the wider CDM framework, our CDM 2015 training covers duties, compliance, and best practice. For quick answers to common questions, our FAQs page is a useful starting point.


Getting notification right is a small task with a large consequence. A missing or late F10 puts the whole project on the back foot from day one.

Frequently Asked Questions

When does a construction project need to be notified to HSE?

A project is notifiable when construction work lasts more than 30 working days and has more than 20 workers on site at the same time, or exceeds 500 person-days of work. These are the two tests set under Regulation 6 of the CDM Regulations 2015. If either test is met, the project is notifiable and an F10 must be submitted to HSE before work begins. Check your planned workforce and duration against both thresholds early in project planning.

Who is responsible for submitting an F10 notification?

The client holds the legal duty to notify HSE, though in practice the principal contractor or principal designer often submits the F10 on the client’s behalf. Responsibility should be agreed in writing at the outset so nothing falls between roles. If project roles change after work starts, confirm who now holds the duty and update the notification. Whoever submits should keep a copy of the confirmation and share it with the principal contractor for the site file.

Do I need to update an F10 notification if project details change?

Yes. If the project duration, maximum workforce, start date, site address or key dutyholders change, update the notification through the HSE online service. The original notice stays on record, so submit a revised version with the corrected details rather than starting again. Keep the updated confirmation with your site records. Reviewing the F10 at each project phase change is good practice and helps show the dutyholder has kept project information current.

What information do I need before completing an F10 form?

Gather the site address and project description, the planned start date and expected duration, the maximum number of workers on site at any one time, and the person-days estimate. You also need contact details for the client, principal designer and principal contractor. Having these ready before you open the online form avoids the session timeout that can lose unsaved changes. Keep a copy of the submitted confirmation for the site notice board.

0 replies

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *

Get in touch

to start your next course
or ask us any question

Call us on 01782 438813
Email us at hello@youcandoit.training
Find us here (What Three Words: star.vines.fantastic)

© Copyright You Can Do It Training LTD. All rights reserved. | Website by Clyq